Upcoming Metrolinx Ontario Line Work in Your Area

Ontario Line Community Notice: Queen-Spadina south site construction update

  • Expected duration: The current excavation cycle, which includes rock breaking and structural work, is expected to continue through early 2026.
  • Hours of Work: As early as November 19, 2025, the hours of work at the south site will be adjusted to reflect the current stage of work and efficiently complete the required excavation activities.
  • Work is expected to start at 7 a.m. and continue up to 2 a.m., Monday through Friday.
  • Crews may also work on Saturday and Sundays from 7 a.m. to 5 p.m. • All work schedules are subject to change, and weather permitting.

Excavation at the Queen-Spadina south site has entered its final stage, with rock breaking and structural work continuing through early 2026. Beginning November 19, 2025, work hours will extend from 7 a.m. to 2 a.m. on weekdays, with weekend shifts as needed, subject to weather and schedule changes.

The reason for the extension is to complete this work as quickly as possible and move into the less intrusive phases of construction. Crews will be using a specialized roadheader that is expected to be quieter than the previous roadheader used, with proven success at other sites. To minimize disruption during extended work hours, crews will primarily rely on this equipment instead of traditional hammer-style excavators, materials will be removed via the Queen-Spadina north site to reduce crane and machinery activity at the south site, and continuous noise and vibration monitoring will remain in place to track impacts. Please see attached notice for more details.

Contact: ontarioline@metrolinx.com


Ontario Line Community Notice: Osgoode station signage installation

Expected start date: Monday, Dec. 1, 2025 
Expected end date: Up to one (1) week
Hours of work: 9 p.m. to 5 a.m., Monday to Friday

Starting as early as December 1, 2025, crews will install signage panels on the hoarding around the construction zone in the median of University Avenue. The work is expected to take up to one week and will occur overnight from 9 p.m. to 5 a.m., Monday through Friday, with possible weekend shifts if needed. To ensure public safety, intermittent partial lane closures will be in place, maintaining four of the five lanes in each direction, while flag-persons and safety barriers will guide pedestrians and separate traffic from the work zone. Clear signage will be posted for transit riders, pedestrians, and motorists, and crews will continue to take measures to minimize noise impacts throughout the installation.

Contact: ontarioline@metrolinx.com


Station Works at King-Bathurst

Expected start date: November 2025 
Expected duration: Three years
Hours of Work: South site: Monday to Friday 7:00 A.M. – 11:00 P.M.
Weekends as needed 8:00 A.M. – 5:00 P.M. North site (Cavern): 24-hour, 7 days a week

Please see the attached updated construction notice for King-Bathurst for station work. The current phase of excavation is nearing completion and will be moving to station works soon. These works include concrete pouring at the station sites and installation of waterproofing membranes where they have not yet been installed. This significant phase of construction will continue for approximately three years, with additional updates and construction notices shared with the community as work continues.

Work hours for this new phase of work will remain the current hours: 7:00 A.M. – 11:00 P.M. weekdays, with 8:00 A.M. – 5:00 P.M. on weekends, with Sundays as optional and only as needed. Residents may see and hear crews arrive on site prior to the start of scheduled work hours for preparatory tasks.

This notice is being shared with community groups, including BIA, 311, and elected officials. This notice will also be posted on our website.

The final Construction Liaison Committee (CLC) meeting for this year for King-Bathurst station is currently scheduled for Thursday, December 4th at 6:00 P.M. Your continued attendance and participation during these meetings has been greatly appreciated. The Ontario Line Community Engagement team recently hosted an in-person King-Bathurst open house on Thursday, November 6th, and due to the recent completion of this event we are requesting feedback from community members on the final CLC meeting for the calendar year. Please indicate by reply which of the following options you prefer:

Option 1: The meeting proceeds as usual, with a presentation on construction updated by OTG along with an open Q&A session afterward for any topics of discussion not covered during the presentation.

Option 2: The presentation deck is distributed to meeting attendees, and community members are free to contact us with any questions or concerns about the material or updated presented in the deck.

CLC meetings for King-Bathurst station will resume as usual in 2026 with meetings held on the first Thursday of every month. Along with your preferred option for the December 2025 CLC meeting, please also indicate your interest in continuing to attend these meetings in 2026.

Contact: Bradley – Bradley.Naismith@metrolinx.com 


Ontario Line Community Notice: Shaft excavation at Osgoode north site

Expected start date: As early as November 12, 2025 
Expected duration: Up to six months
Hours of work: 24 hours a day, seven days a week

Please see the attached notice for upcoming shaft excavation work at the Osgoode station north site, starting as early as November 12, 2025, and expected to continue for up to six months.

Crews will move into Phase 2 excavation of the bedrock for the future Ontario Line station. This work will take place 24 hours a day, seven days a week, including weekends. During this phase, residents and businesses can expect to see cranes, excavators, dozers, and dump trucks in use on-site, with increased truck traffic entering and exiting the area daily following specified haul routes. Additional lighting will be installed to support safe working conditions overnight.

No new impacts to pedestrian or vehicle access are expected as part of this phase. Closures related to the cladding works on University Avenue and the Queen Street West access gate installation remain in place, as outlined in the notice issued on August 29, 2025. Mitigation measures are in place to reduce construction impacts, including noise and vibration monitoring, air quality monitoring, acoustic shelters, plywood hoarding, and mud mats for dust suppression. Paid duty officers and traffic control personnel will be on site as needed to support public safety.

Contact: ontarioline@metrolinx.com


Osgoode Station North Site Excavation Works

Please find attached an updated version of the construction notice for excavation works at the Osgoode Station north site, indicating a new nightly temporary sidewalk closure on Queen Street for the month of October.

This temporary closure of the westbound curb lane on Queen Street West between York Street and University Avenue will support the installation of a new acoustic shelter site entrance and the TTC stop relocation pedestrian curb cut installation. It will take place on weekdays from 9 p.m. to 5 a.m. until the end of October.

Crews continue to work weekdays and weeknights (and weekends as required) from 7 a.m. to 7 p.m. and from 7 p.m. to 7 a.m. (24 hours) until the end of November 2025.

Traffic signage will be posted. Traffic control person(s) will be on site as required to ensure the safety of pedestrians.

Work may be postponed, extended, or rescheduled due to weather or other unforeseen circumstances.  

Construction Details:

  • Closures of the bike lane and pedestrian path on University Avenue are ongoing nightly on weekdays 9 p.m. to 5 a.m. until the end of November 2025
  • Temporary northbound lane closures on University Avenue, Friday nights to Monday morning, from 9 p.m. to 5 a.m. until the end of November 2025
  • Temporary sidewalk closure on Queen Street West: Nightly on weekdays 9 p.m. to 5 a.m. until the end of October 2025
  • Contact: 416-202-5100 | ontarioline@metrolinx.com

Graffiti Alley Closure & Open House

Please see the attached notice for Graffiti Alley closures, starting as early as October 6, 2025.

To support construction of the Ontario Line at Queen-Spadina, crews will occasionally need to close Graffiti Alley for equipment and material deliveries. Deliveries will only be scheduled between 9:00 A.M. and 4:00 P.M. weekdays and are expected to be completed within two hours. These deliveries can occur between now and approximately October 2026. Residents can expect to hear noise from trucks delivering equipment and material during these deliveries. A crane will be used to move material from Graffiti Alley to the station site.

This notice also contains information on our upcoming in-person open house for Queen-Spadina station on Thursday, October 30, 2025 at Ogden Junior Public School, 33 Phoebe St.

Open House:
When: Thursday, Oct. 30, 2025
Time: 6:15 P.M. – 7:30 P.M.
Location: Ogden Junior Public School

Closure Details

  • Expected installation start date: As early as Oct. 6, 2025 
  • Expected duration: Through October 2026
  • Work hours: 9 A.M. to 4 P.M.
  • Contact: ontarioline@metrolinx.com

Notice of Excavation

Please find an attached construction notice to accommodate work serving the future Ontario Line King-Bathurst Station. 

Work crews are advancing excavation at the King-Bathurst south site, removing soil and bedrock to a depth of 40 metres to create the future Ontario Line station site. As spoils are removed, a shaft (the excavated open area) has been created. This work is completed in sequence, with coordinated phases of rock breaking followed by installation of structural reinforcements. 

Crews are preparing to start the next phase of excavation including rock breaking beginning as early as May 2, 2025. This phase of work is expected to take approximately eight weeks to complete. At which point, the next phases of structural support will be installed. There will be lighting in place to support evening work. While most lights will turn off once work is complete, some lighting will remain on overnight for safety and security at the site. 

All the necessary permits have been obtained. Equipment demobilization may be postponed or rescheduled due to unforeseen circumstances.

  • Expected start date: As of May 2, 2025

  • Duration: Through late 2025
  • 
Hours of work: Monday through Friday, from 7:00 a.m. through 11:00 p.m., and Saturdays from 8:00 a.m. through 5:00 p.m. Some work will occur on Sundays as needed, from 8:00 to 5:00 p.m.

Station Excavation & Cavern Work at Queen & Spadina

Please see the attached construction notice for updated cavern work at Queen and Spadina, including working hours on Saturday, February 8th, and Sunday, February 9th, 2025 from 7:00 A.M. to 5:00 P.M.

Crews are excavating a cavern to connect the station shaft to the future Ontario Line tunnel. This is done using equipment known as a road header. Excavated dirt, known as spoils, will be loaded into trucks and transported out of the city for safe disposal. All possible mitigations are in place, including noise & vibration monitoring, limits on vehicle idling, and site hoarding.

This notice is being shared with community groups, including BIA and 311. This notice will also be posted on their website. Please don’t hesitate to contact them with any questions or concerns about this notice.

  • Expected start date: February 2025
  • Hours of work: 24-hour shifts (Monday – Saturday), with occasional Sunday work as needed. Expected Completion: Early 2026
  • Contact: Ontario Line Metrolinx | ontarioline@metrolinx.com | 416-202-5100

Notice of Excavation and Cavern Work

Please see the attached construction notice for excavation and cavern work at Queen/Spadina station, with new work hours effective until early 2026.

Crews will be working underground to excavate the station cavern, which will connect the completed shaft at the north station site to the future tunneling route. Specialized equipment will be brought to the site and assembled before operation can begin. Spoils excavated from the cavern will be loaded on to trucks and hauled away from the site. The new work hours are 24-hour work, Monday-Saturday. No work is currently expected to take place on Sunday. Residents can expect noise and dust from the site crew as various equipment is used. A series of monitors and mitigation equipment is installed on-site to prevent excessive noise or dirt and dust spreading into the community.

This notice is being distributed to community groups, including BIA, elected officials, and 311. This notice will also be posted on their website. Please don’t hesitate to reach out to them with any questions or concerns about this work.

  • Expected start date: December 2024
  • Hours of work: 24-hour shifts (Monday – Saturday) 
  • Expected Completion: Early 2026
  • Contact: Ontario Line Metrolinx | ontarioline@metrolinx.com | 416-202-5100

Cavern and Excavation Work

Please see the attached construction notice for cavern and excavation work at King and Bathurst, starting as early as early December, 2024.

Crews will continue to excavate the future King/Bathurst station north site, connecting the current shaft to the location of the Ontario Line tunnels. Specialized equipment known as a roadheader will be delivered to the site and assembled before work will commence. Rock spoils will be loaded into trucks and transported away from the work site.

Work will be taking place 24/7, all within the acoustic shelter currently in place at the north site. Noise and vibration will be constantly monitored through a series of devices set up around the site to ensure acceptable levels at all times.

This notice is being shared with the community, including BIA, elected officials, and 311. This notice will also be posted on our website. Please don’t hesitate to reach out with any questions or concerns about this work.

  • Expected start date: December 2024
  • Hours of work: 24-hour work shifts, 7 days a week 
  • Expected Completion: Late 2025
  • Contact: Ontario Line Metrolinx | ontarioline@metrolinx.com | 416-202-5100